AAC Block Quantity Calculator

Block count, volume and adhesive from wall size and block format.

Inputs

m
m
m²
mm
mm
mm
2-4 mm for thin-bed adhesive, 15 mm with ordinary mortar
%

Result

Formula

Net areaA = length × height − openings
Blocks per m²n = 1 ÷ ((length + joint) × (height + joint))
Total blocksN = ceil(A × n × (1 + waste))
MortarV = wall volume − blocks × block volume
Per m³n ÷ wall thickness
A 10 m × 3 m wall, 200 mm thick, 600×200×200 blocks with 3 mm joints and 3% waste: 8.17 blocks per m², 253 blocks in total, 6.00 m³ of wall and about 0.05 m³ of mortar.

AAC block formats and blocks per square metre (3 mm joints)

Format L×H×T (mm)Blocks per m²Blocks per m³Weight per block (kg)
600×200×1008.1781.77.5
600×200×1508.1754.511.3
600×200×2008.1740.815.0
600×200×2508.1732.718.8
600×250×2006.5232.618.8
600×300×2005.4227.122.5

FAQ

Why not use ordinary cement mortar with AAC?
Ordinary mortar needs 15 mm joints, shrinks more and is stiffer than AAC, so it cracks at the joints; AAC also draws water out fast, leaving the mortar weak. Use thin-bed adhesive at 2-4 mm, fully bedded, and never stronger than the block itself.
Should AAC blocks be wetted before laying?
No — the key difference from fired brick. AAC absorbs slowly, and wetting leaves the surface saturated so the adhesive cannot cure properly, reducing strength; excess water also causes shrinkage cracking. Brush off dust, and in hot dry weather mist lightly but leave no free water.
What waste allowance should I use?
3% for plain walls with a uniform format, 5-8% where there are many openings, corners and irregular areas, and 10% where much cutting is needed. AAC cuts easily but breaks easily, and transit damage counts too — 100 mm boards break far more than thicker ones.