算BuildCalc

Slope Converter

Enter rise and run to get the slope as a percentage, in degrees, as a ratio and as rise per metre.

Inputs

m
Difference in elevation between two points
m
Horizontal distance, not the slope length

Result

Formula

Slopei = rise ÷ run
Percentageslope % = i × 100
Angleθ = arctan(i)
Ratio1 : n where n = 1 ÷ i
Slope lengthL = √(rise² + run²)
A 1 m rise over 10 m run: 10% slope, 5.71°, ratio 1:10, 100 mm per metre, and a slope length of 10.05 m.

Slope conversion table

SlopeAngleRatioRise per metreTypical use
0.5%0.29°1:2005 mmSurface drainage
1%0.57°1:10010 mmGutters and eaves
2%1.15°1:5020 mmFlat roof falls
3%1.72°1:33.330 mmStructural falls
5%2.86°1:2050 mmProfiled metal roofs
10%5.71°1:10100 mmMax. accessible ramp
20%11.31°1:5200 mmAsphalt shingle roofs
33%18.26°1:3330 mmPlain tile roofs
50%26.57°1:2500 mmSteep pitched roofs
100%45.00°1:11000 mm45° pitched roof

FAQ

Should I use percent or degrees?
Percent (or per mille) suits earthworks, roads and drainage because you can compute fall directly from horizontal distance, which is how you set out. Degrees suit steelwork and machine installation where the angle between members matters. Roofs are usually given as a ratio. The conversion is percentage = tan(angle) × 100, so 45° is 100%, not 90%.
What roof slopes are typical?
Flat roofs are graded at least 3% structurally or 2% with a screed, and gutters need at least 1% longitudinal fall. Tiled roofs depend on the covering: plain tiles about 20-50%, asphalt shingles at least 20%, profiled metal at least 5%. Insufficient fall on flat roofs is the single biggest cause of leaks.
What is the most common setting-out mistake?
Using the slope length as the run. Measuring 10 m along the slope when the horizontal distance is only 9.96 m makes the gradient read high. Measure the run horizontally with a level or total station, or derive l = rise ÷ i first. Also check that drainage falls toward the outlet, not away from it.

Related calculators

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.